Invoice or Payment? One Mistake in a Construction Contract That Blocks Settlement with Subcontractors

Learn why linking invoicing to subcontractor documents creates conflicting clauses, and how to separate invoicing from payment in Polish construction contracts.

The client’s question sounded like a question about commas: “can we accept the wording proposed by the contractor?”. In reality, it was a question about whether the contracting authority would pay twice for the same work.

In the general contracting agreement, one paragraph prohibited issuing an invoice without subcontractor declarations, while the next governed the withholding of payment for an invoice that — under the preceding paragraph — should never have been issued. The provisions could not be reconciled. And this is no exception. It is a pattern repeated in dozens of active construction contracts — both public and private.

The scale of the problem is serious. Data from parliamentary question No. 10867 indicate that construction companies have debts of approximately PLN 1.35 billion, more than 192,000 unpaid liabilities, and approximately 43,312 debtors in the sector (Parliamentary question No. 10867). Not every one of these disputes results from poorly drafted subcontracting clauses — but every defective clause increases the risk that your company will become part of these statistics.

In this article, I will explain where this mistake comes from, why it is so common, and how to fix it — without rewriting the agreement from scratch. You will also learn what a subcontractor declaration should contain, how to amend an agreement safely under the public procurement regime, and how to check whether your active contracts have exactly the same problem.

Key concepts before we continue

Before moving on to the diagnosis and solution, it is worth clarifying several terms that appear in every construction contract involving subcontractors.

Concept What it means in the context of this article
Investor’s joint and several liability The investor is liable for the subcontractor’s remuneration on an equal footing with the general contractor — even if the investor has already paid the contractor for the same work. This follows from Article 647¹ of the Civil Code.
Acceptance report A document confirming that the contracting authority has accepted a specified scope of work. This is the event that should trigger the right to issue an invoice.
Subcontractor declaration Written confirmation from the subcontractor that it has received payment for the work performed. It serves as evidence — protecting the contracting authority against double payment.
Direct payment to the subcontractor (Article 465 of the Public Procurement Law) In public procurement, the contracting authority has a statutory obligation to pay the subcontractor directly when the contractor fails to make payment. This obligation cannot be excluded by contract.
Material modification of the agreement (Article 454(2) of the Public Procurement Law) A modification that could, among other things, have attracted other contractors, disrupts the economic balance, or substantially changes the scope of the obligations. A clarifying amendment should not meet these criteria.

Invoice versus payment — two events, two functions

This is the crux of the problem. Issuing an invoice and making a payment are two separate legal events that serve different functions:

  1. Issuing an invoice — an act by the contractor documenting performance of the obligation. It is based on acceptance of the work, confirmed by an acceptance report.
  2. Payment — an act by the contracting authority to settle the liability. It may be made subject to additional conditions, including the submission of subcontractor documents.

When an agreement makes the right to issue an invoice dependent on settling accounts with subcontractors, it introduces the condition one step too early. A contractor that has delivered the work and obtained an acceptance report is formally unable to issue an invoice — because it is waiting for a subcontractor declaration over which it often has no control.

What the defective structure looks like

Step in the process Defective structure Correct structure
Acceptance of work Report signed ✓ Report signed ✓
Issuing the invoice Blocked — subcontractor declarations missing Permitted — based on the acceptance report
Submission of subcontractor documents Required before invoicing Required before payment
Payment period Does not begin (no invoice) Begins on the date the complete set of documents is submitted
Payment Blocked twice over Conditional on submission of the complete set of documents

The defective structure creates a contradiction: one paragraph of the agreement prohibits issuing an invoice without subcontractor documents, while the next governs the withholding of payment for an invoice. If the invoice should not exist, the provision on withholding payment is redundant. And if the contractor issues the invoice anyway — the contracting authority does not know which paragraph to apply.

What risks does this drafting error create?

Risk of joint and several liability — double payment

Article 647¹ § 1 of the Civil Code provides for the joint and several liability of the investor and contractor for the subcontractor’s remuneration if the detailed scope of the work was reported to the investor before that work commenced (Journal of Laws of 2026, item 795 — consolidated text of the Civil Code). The investor may release itself from this liability by raising an objection within 30 days of receiving the notification (an amendment introduced by Journal of Laws of 2025, item 1508).

A defective documentation mechanism does not replace this statutory procedure. If the notification was made correctly and the contractor failed to pay the subcontractor — the investor is jointly and severally liable, regardless of the wording of the contractual clause.

The liability is capped at the lower of two amounts: the subcontractor’s remuneration under its agreement with the contractor and the remuneration due to the contractor for the corresponding scope of work (Article 647¹ § 3 of the Civil Code). But even this amount, multiplied by several subcontractors, may represent a serious financial burden.

Risk of interest for late payment

Without a clause suspending the payment period until the complete set of subcontractor documents has been submitted, the situation is as follows:

  1. The contractor issues an invoice after acceptance.
  2. The payment period begins when the invoice is delivered.
  3. The contracting authority does not pay because it is waiting for subcontractor declarations.
  4. The deadline passes — the contracting authority falls into default.
  5. Statutory interest for late payment in commercial transactions begins to accrue.

The Act on Counteracting Excessive Delays in Commercial Transactions imposes payment deadline limits that vary according to the status of the parties. In an SME–large enterprise relationship, a deadline exceeding 60 days is invalid by operation of law (Journal of Laws of 2023, item 1790). A clause that effectively extends the payment deadline beyond this limit may be challenged.

Risk of an interpretative dispute over every invoice

Contradictory provisions in adjacent paragraphs of the agreement mean that every invoice becomes subject to negotiation:

  1. The contractor relies on the paragraph concerning the withholding of payment — and issues an invoice.
  2. The contracting authority relies on the paragraph prohibiting invoicing — and refuses to accept it.
  3. Both parties are right and both are wrong — because the provisions cannot be reconciled.

Case law confirms that courts accept the temporary withholding of payment until subcontractor documents are submitted. In judgment I CSK 408/17, the Supreme Court classified such a mechanism as a temporary withholding of payment until a formal condition has been met, distinguishing it from a definitive refusal to pay (Supreme Court judgment I CSK 408/17). However, there is no established line of case law for a model in which the issuing of the invoice itself — rather than payment — is blocked.

Risk of disproportionate withholding

Withholding payment of the entire invoice because one declaration from a low-value service subcontractor is missing is disproportionate and itself open to dispute. The correct structure should provide for withholding only the portion corresponding to the total amounts covered by the missing documents.

 

What the correct structure should look like

The solution does not require rewriting the agreement from scratch. It requires separating the two events and assigning the appropriate conditions to each.

Step 1: basis for issuing the invoice — the acceptance report

State expressly in the agreement that the basis for issuing a partial or final invoice is acceptance of the work, confirmed by a report. No additional conditions should apply. The contractor issues the invoice after the report has been signed — this is the event documenting performance of the obligation.

Step 2: condition for payment — complete set of subcontractor documents

Payment is conditional on the submission of both of the following documents for each subcontractor covered by the requirement:

  1. Printout of the completed bank transfer — confirmation that the contractor transferred the remuneration to the subcontractor.
  2. Subcontractor’s declaration confirming receipt of payment — based on the template attached to the agreement.

State expressly that submitting only one of these documents does not satisfy the condition for payment. This eliminates disputes over whether proof of the transfer alone is sufficient.

Step 3: clause suspending the payment period

The payment period begins only on the date the complete set of documents is submitted. Until then, the invoice is deemed not to have been duly delivered. Without this clause, separating the two events works to the contracting authority’s disadvantage — the payment period runs irrespective of settlements with subcontractors.

Step 4: proportional withholding

Payment is withheld only in an amount equal to the total amounts covered by the missing documents — not the entire invoice. This protects the contracting authority without preventing the contractor from receiving payment for work that has been fully documented.

Step 5: entities covered by the mechanism

Define who is covered by the documentation requirement:

Type of performance Threshold for applying the mechanism
Construction work From the first złoty — no value threshold
Supplies and services Above the monetary threshold specified in the agreement, with a clear list of exclusions

Without this distinction, every invoice triggers a discussion about which subcontractors are subject to the requirement — including suppliers of office materials or cleaning services.

Step 6: restate the rule as a standalone prohibition

Add a separate paragraph stating the rule expressly: the contracting authority will not pay any part of the remuneration until the complete set of documents has been submitted. This repetition is intentional — it makes the agreement easier to apply for those who do not read it in its entirety. The site manager, accountant, supervising inspector — each of them should be able to find the rule without analysing the entire contract.

What should a subcontractor declaration contain?

Article 647¹ of the Civil Code does not provide an official template for a subcontractor declaration or an exhaustive list of its required elements (Journal of Laws of 2026, item 795). Without a template attached to the agreement, each subcontractor submits a different declaration — and the completeness of the documents becomes a matter of dispute with every payment.

Recommended elements of the declaration template:

No. Element of the declaration Function
1 Declarant’s details (company, address, tax identification number, signatory and their authority) Identification of the subcontractor
2 Identification of the subcontract (number, date, parties) Link to a specific contract
3 Type of performance (construction work / supplies / services) Determining the scope of the mechanism
4 Invoice number and the period it covers Allocation to a specific settlement
5 Declaration confirming receipt of all remuneration due and payable Proof of payment
6 Declaration that there are no outstanding due and payable claims Eliminating the risk of further claims
7 Table of invoices with payment dates Verifiability — a statement that can be compared with bank statements
8 Clause acknowledging liability for making a false declaration Prevention — the subcontractor confirms that it is aware of the consequences

Attach this template to the agreement. This eliminates negotiations over every payment and gives the contracting authority a consistent verification standard.

Amending an agreement under the public procurement regime

If your agreement is governed by the Public Procurement Law, changing the payment clauses requires additional care. Article 454(2) of the Public Procurement Law defines a material modification as one that could, among other things, have attracted other contractors, disrupts the economic balance in favour of the contractor, or substantially changes the scope of the obligations (Journal of Laws of 2026, item 793).

The National Appeals Chamber assesses amendments according to their actual effect, not their name. In case KIO/KD 2/23, the Chamber challenged an amendment modifying the functional and utility programme as a change in scope (Judgment KIO/KD 2/23). Simply calling a modification a “clarification” does not prevent it from being classified as a material modification.

What to include in the preamble to the amendment

The justification that the modification is non-material within the meaning of Article 454(2) of the Public Procurement Law should cover the following:

  1. The modification is clarificatory — it resolves a contradiction between existing paragraphs and does not introduce new obligations.
  2. The remuneration, deadlines, and scope of the contract remain unchanged.
  3. The economic balance between the parties is not disrupted.
  4. The overall nature of the agreement remains unchanged.
  5. A reference to the contractual modification clause (if the agreement contains one).

This is not merely decorative. It is evidence in the event of an audit — particularly where funding from national or European budgets is involved.

It is worth remembering that Article 465 of the Public Procurement Law establishes a statutory obligation for the contracting authority to make direct payment of due and payable remuneration to a subcontractor when the contractor fails to pay (Public Procurement Office commentary on Article 465). This obligation cannot be excluded or limited by a contractual provision. The agreement may clarify the procedure (document formats, administrative deadlines), but it cannot make direct payment conditional on requirements not provided for by law.

Ratifying the acts of an unauthorised person

When reviewing the payment clauses, it is worth checking one more point: who actually signed the acceptance reports and declarations in ongoing projects.

If the reports, declarations, or letters were signed by a person who was not identified in the agreement as an authorised contact — there is a risk that the validity of those documents may be challenged. And the entire settlement process relies on the acceptance reports.

Confirming the validity of that person’s acts by means of an amendment with retroactive effect from a specific date is cheaper than a dispute over the effectiveness of an acceptance report. The amendment should:

  1. Identify the person and the date from which they performed the role.
  2. List the categories of acts being ratified (reports, declarations, letters, arrangements).
  3. Confirm the validity of those acts with retroactive effect.

Checklist — review your active agreements

The checklist below will allow you to determine for yourself whether your agreements contain the error described in this article. Work through it for every active agreement involving a chain of subcontractors.

No. Checklist question If the answer is “yes”
1 Does the agreement make issuing an invoice conditional on subcontractor documents (declarations, proof of transfer)? Move this condition to the payment requirements
2 Does the agreement contain contradictory paragraphs — one prohibiting invoicing and another governing the withholding of payment for an invoice? Resolve the contradiction by amendment
3 Does the payment period begin upon delivery of the invoice without a suspension clause? Add a clause stating that the period begins on the date the complete set of documents is submitted
4 Does the agreement require both documents together (transfer + declaration), or only one? State the cumulative requirement expressly
5 Is a subcontractor declaration template attached to the agreement? Prepare and attach a template as an appendix
6 Are the entities covered by the mechanism defined (construction work vs. supplies and services, monetary threshold)? Clarify the scope and exclusions
7 Is the withholding of payment proportional (part of the invoice), or does it apply to the entire amount? Change it to proportional withholding
8 After one paragraph was amended, were the adjacent provisions checked for contradictions? Review the context of every amended drafting unit
9 Were the acceptance reports signed by a person identified in the agreement? If not — ratify the acts by amendment
10 (Public procurement only) Does the preamble to the amendment justify why the modification is non-material? Include the justification and cite the modification clause

A targeted correction to one paragraph without reviewing the adjacent provisions is the most common source of this type of error. Every change to a single condition requires a review of its context.

Does this mechanism work outside the construction sector?

Article 647¹ of the Civil Code and Article 465 of the Public Procurement Law apply to construction work. However, similar back-to-back clauses — making payment conditional on the counterparty settling accounts with its subcontractors — are also used in IT, outsourcing, and SaaS projects involving chains of subcontractors.

Article 89 of the Civil Code permits the effects of a legal act to be made conditional on a future and uncertain event, but Article 94 of the Civil Code provides that a condition contrary to the law or the principles of social coexistence is invalid (Journal of Laws of 2024, item 1061).

A back-to-back clause in IT contracts is contractually permissible, but it does not benefit from the statutory protection applicable to construction subcontracting. A safer structure is to set a maximum payment deadline independent of the client’s decision — so that the condition does not result in the claim remaining indefinitely not due and payable.

If your company uses chains of subcontractors in IT or outsourcing projects, check whether the payment clauses transfer the risk of the client’s insolvency to the subcontractor without any time limit.

Check whether your agreement contains this error

The problem described here affects public contracting authorities and private investors alike, as well as general contractors and companies using chains of subcontractors in IT or outsourcing. Fixing it does not require rewriting the agreement — it requires a precise amendment that separates invoicing from payment and resolves the contradictions.

If, after working through the checklist, you can see that your agreements need to be corrected — or you are unsure how to assess the provisions — contact us. We will audit your payment clauses, prepare a subcontractor declaration template, and help you draft an amendment — including under the public procurement regime.

Frequently asked questions

Can I prohibit the contractor from issuing an invoice for work that I have already accepted by signing an acceptance report?

Such a provision is difficult to defend. Issuing an invoice documents performance of the obligation — and that performance has been confirmed by the acceptance report. Case law confirms that payment may be withheld temporarily (Supreme Court judgment I CSK 408/17), but it does not confirm that blocking invoicing itself is effective. It is safer to make payment — rather than invoicing — conditional on the subcontractor documents.

When does the payment period begin if the invoice is valid but the subcontractor declarations are missing?

If the agreement does not contain a suspension clause, the period begins when the invoice is delivered — and the contracting authority falls into default despite the outstanding settlements with subcontractors. The agreement should therefore state expressly that the payment period begins on the date the complete set of documents is submitted and that, until then, the invoice is deemed not to have been duly delivered.

Is proof of the transfer sufficient, or do I also need a subcontractor declaration?

The safest approach is to require both documents together. Proof of the transfer demonstrates that the money was sent — but it does not demonstrate that the subcontractor considers its remuneration to have been paid in full. The subcontractor declaration eliminates the risk of further claims. The agreement should state expressly that submitting only one document does not satisfy the condition for payment.

Can I withhold the entire invoice if one document is missing?

Withholding the entire invoice because one declaration is missing is disproportionate and may itself become the subject of a dispute. The correct structure provides for withholding only the portion corresponding to the total amounts covered by the missing documents — not the entire amount.

How can such revisions be incorporated into an amendment under the public procurement regime?

Include a justification in the preamble to the amendment stating that the modification is not material within the meaning of Article 454(2) of the Public Procurement Law: it is clarificatory, introduces no new obligations, does not change the remuneration, deadlines, or scope, does not disrupt the economic balance, and does not alter the overall nature of the agreement. Cite the contractual modification clause. The National Appeals Chamber assesses an amendment according to its actual effect — simply calling it a “clarification” is not enough, but if the modification genuinely resolves a contradiction without changing the scope, the justification should be sufficient.

What should I do if the acceptance reports were signed by someone who is not identified as authorised in the agreement?

Ratify that person’s acts by means of an amendment with retroactive effect from the date on which they began performing them. The amendment should identify the person, list the categories of acts (reports, declarations, letters, arrangements), and confirm their validity. This is cheaper than a dispute over the effectiveness of the acceptance report on which the entire settlement process relies.